Control Analysis of the Griya Jenggala Development Project using the Earned Value Method at PT Sarana Loka Almika in Kebayoran
DOI:
https://doi.org/10.28932/ice.v4i3.7346Keywords:
development of Griya Jenggala, PT Sarana Loka Almika, project controlAbstract
Project control is a structured effort to establish standards in accordance with the plan, design information systems, compare implementation with established standards, analyze potential deviations, and take corrective actions necessary to ensure the effective and efficient use of resources in line with the set targets. Each project has its own specific plan and schedule, determining the start and end time of the project, implementation methods, and resource allocation. Operational challenges often arise in project planning, such as resource shortages, improper allocation, delays, and other issues that may hinder the achievement of project goals as planned. This research utilizes a descriptive quantitative approach, which is a research method that describes the specific conditions of the project through the analysis of available data. This article will discuss the cost variance (CV) and schedule variance (SV) in the development of Griya Jenggala at PT. Sarana Loka Almika, evaluate the cost performance index (CPI) and schedule performance index (SPI) in the development of Griya Jenggala to assess its effectiveness, estimate the cost at completion (EAC) and estimated duration at completion (EAS) required to complete the Griya Jenggala project, as well as provide an estimation of potential profits or losses that may arise in the Griya Jenggala development project.References
Agatha, K., & Dani, H. (2018). Pengendalian biaya dan jadwal proyek dengan menggunakan nilai hasil (proyek rehabilitasi Gedung X Gresik). Jurnal Rekayasa Teknik Sipil, 2(2).
Aziz, A., Pinem, D., Tubagus, S., Nurmatias, & Argo, J. G. (2022) Manajemen proyek (tinjauan teori dan praktis). Penerbit Widina. https://repository.penerbitwidina.com/ media/publications/554356-manajemen-proyek-tinjauan-teori-dan-prak-2742d9d9.pdf
De Marco, A., & Narbaev, T. (2013). Earned value-based performance monitoring of facility construction projects. Journal of Facilities Management, 11(1), 69–80. https://doi.org/10.1108/14725961311301475
Dewantoro, G. dan N. (2018). Earned value analysis terhadap pengendalian kinerja proyek ( Studi kasus proyek operasi dan pemeliharaan SDA Serayu Opak). Prosiding Kolokium Program Studi Teknik Sipil (KPSTS).
Hasiyah, S. (2018). Analisis waktu pada proyek pembangunan Apartemen Taman Melati Surabaya @ Merr dengan earned value method. Universitas 17 Agustus 1945.
Kerzner, H. (2019). Using the project management maturity model: strategic planning for project management. John Wiley & Sons.
Lumentah, C. N., Arsjad, T. T., & Malingkas, G. Y. (2020). Pengendalian biaya dan waktu pada proyek pembangunan ruko di area Perumahan Kharisma Koka Minahasa menggunakan metode konsep nilai hasil. Jurnal Sipil Statik, 8(1), 53-64.
Meliasari, I., Indrayadi, M., & Lusiana (2011). Earned Value Analysis terhadap biaya dan waktu pada proyek konstruksi. Jurnal Mahasiswa Teknik Sipil Universitas Tanjungpura, 2(2). https://jurnal.untan.ac.id/index.php/JMHMS/article/download/ 3982/3993
Monica, V. A. (2013). Praktek perencanaan dan pengendalian biaya proyek pada kontraktor di Nunukan Kalimantan Timur. Universitas Atma Jaya Yogyakarta.
Rani, H. A. (2016). Manajemen proyek konstruksi. https://www.researchgate.net/publication/ 316081639_Manajemen_Proyek_Konstruksi
Ruslan, W. (2019). Manajemen proyek jaringan. Universitas Katolik Atma Jaya Jakarta. Sinaga, Y. (2014). Praktek perencanaan dan pengendalian biaya proyek pada kontraktor di
Balikpapan Kalimantan Timur. Universitas Atma Jaya Yogyakarta.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Heni Nastiti, Denta Sawwath Suryana, Fattan Rahmat Firza Aulia , Muhammad Rayhan Ramsyahdira
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.