Reducing The Number of Intermediate Stock by Implementing Just-In-Time & Pulling System

Main Article Content

Lisna Nuraini
Athina Sakina Ratum

Abstract

In tire manufacturing process in PT. XYZ, there is an area called the Intermediate Area in the Building - Curing area where WIP materials are temporarily stored before proceeding to the Curing process. The capacity of Intermediate Area is 15000 pcs, and the daily production volume approximately 20000 pcs. As a result, more space in the Intermediate Area is required to accommodate the increasing tire production planning. In this study, JIT & Pull system improvement process is carried out by following the PDCA cycle methodology. The implementation of the JIT done by determining standard for the number of intermediate stocks, whereas the Pull system implementation done by setting the standard material handling cycle time standard for one cycle. To keep the improvement runs according to the plan, the guidance sheet is made as the reference of the process. These improvements done to achieve the objective which is to reduce the number of stocks in the Intermediate Area by up to 834 pcs per day and reduce the total cycle time from 110 minutes to 90 minutes. Therefore, the main contribution of this research is to reduce the number of WIP materials in intermediate area and reduce the excessive transportation in the material handling process.

Downloads

Download data is not yet available.

Article Details

How to Cite
Nuraini, L., & Ratum, A. S. (2024). Reducing The Number of Intermediate Stock by Implementing Just-In-Time & Pulling System. Journal of Integrated System, 7(1), 52–62. https://doi.org/10.28932/jis.v7i1.8914
Section
Articles

References

Azim, A. (2018) ‘Just-in-Time (JIT) - pull system approach on a Malaysia Rubber Production Company’, International Journal of Advances in Scientific Research and Engineering, 4(8), pp. 139–149.

Bazrkar, A. and Iranzadeh, S. (2017) ‘Prioritization of Lean Six Sigma improvement projects using Data Envelopment Analysis Cross Efficiency Model’, Quality - Access to Success, 18(157), pp. 72–76.

Gupta, V. (2015) ‘Lean Manufacturing: a review’, International Journal of Science Technology & Management, 3(2), pp. 176–180.

Halim, N.H.A. et al. (2015) ‘Effective material handling system for JIT automotive production line’, Procedia Manufacturing, 2, pp. 251–257.

Huang, C.L. et al. (2014) ‘A comparative study of Pull and Push Production methods for Supply Chain Resilience’, International Journal of Operations and Logistics Management, 3(1), pp. 1–15.

Isniah, S., Purba, H.H. and Debora, F. (2020) ‘Plan do check action (PDCA) method: literature review and research issues’, Jurnal Sistem dan Manajemen Industri, 4(1), pp. 72–81.

Jaffar, A. et al. (2015) ‘Management of seven wastes: a case study in an automotive vendor’, Jurnal Teknologi (Sciences & Engineering), 76(6), pp. 19–23.

Kumar, S. (2014) ‘Lean Manufacturing and its implementation’, International Journal of Advanced Mechanical Engineering, 4(2), pp. 231–238.

Mankazana, S. and Mukwakungu, S.C. (2018) ‘The impact of Just-in-Time (JIT) in Inventory Management System and the supplier overall performance of South African’s bed mattress manufacturing companies’, in International Conference on Industrial Engineering and Operations Management. Johannesburg.

Neyestani, B. (2017) ‘Seven basic tools of Quality Control: the appropriate techniques for solving quality problems in the organizations’, pp. 1–10. Available at: https://doi.org/10.5281/zenodo.400832.

Nwaiku, M.S. and Ejechi, J. (2022) ‘Inventory Management practices and organizational productivity in Nigerian manufacturing firms’, Journals of Entrepeneurship and Business, 10(2), pp. 1–16.

Priniotakis, G. and Argyropoulos, P. (2018) ‘Inventory Management concepts and techniques’, in IOP Conference Series: Materials Science and Engineering 459 012060.

Rina, Syamsudin, A. and Hidayat, D.R. (2021) ‘Analisis implementasi sistem Just In Time (JIT) pada persediaan bahan baku untuk memenuhi kebutuhan produksi pada Zidane Meubel Palangka Raya’, Jurnal Manajemen Sains dan Organisasi, 2(1), pp. 64–72.

Shahriar, F. (2019) Performing time study in workplace. Available at: https://doi.org/10.13140/RG.2.2.25339.77604.

Shedge, D.G. et al. (2022) ‘Muda Mura and Muri analysis’, International Journal of Engineering Development and Research, 10(2), pp. 84–91.

Wani, Z., Chin, J. and Muhammad, N. (2019) ‘Common mistakes in running PDCA: a survey on university student PDCA Projects’, in IOP Conference Series: Materials Science and Engineering 530 012042. Series: IOP Publishing. Available at: https://doi.org/10.1088/1757-899X/530/1/012042.