Analysis Of The Effect Of Contract Changes Order (Addendum) Due To Force Majeure Using SPSS And SmartPLS
(Case Study: BKS-LPD Project Karangasem Regency)
DOI:
https://doi.org/10.28932/jts.v19i1.5256Keywords:
Addendeum, Cost, Force Majeure, SmartPLS, SPSS, Time, QualityAbstract
Due to delays brought on by force majeure, the BKS-LPD Building Construction Project required a contract change order (addendum) to give the service providers a chance to finish the work. According to earlier studies, contract change orders (addendum) have an impact on the price and timeline of the work. The aim of the research is to use the SPSS and SmartPLS tools to find out the result of the impact of the contract change ordered due to force majeure. The research method utilized consists of retesting the questionnaire's results from earlier research utilizing the SPSS and SmartPLS computer tools. The purpose of the retesting is to identify any differences between the analysis results from the SmartPLS program and the analysis results from earlier research conducted using SPSS, as well as to evaluate the precision of each statistical software. According to the results of the SPSS, the addendum significantly affects costs by 12.6%. Only by 4.9% and 0.4% did the addendum's impact on quality and time become insignificant. The analysis's results for the SmartPLS program revealed that the addendum significantly impacted cost and quality by 11.9% and 12.6%, respectively. The addendum's impact is insignificant because it is just 0.4% on time. Differences in margins or limitations on validity test requirements that are quite dissimilar in the need to qualify for each of these statistical programs lead to differences in analysis results between the SPSS and SmartPLS programs, especially in the relation of addendums to quality. Due to this, while using the SmartPLS tool for analysis, several variable indicators were left out.Downloads
References
Baskoro, A. T., & Sihombing, L. B. (2021). Kajian Faktor Dan Variabel Penting Penyebab Cost Overrun Pada Proyek Konstruksi Bangunan Gedung Yang Dapat Dikendalikan Dengan Penggunaan Bim. Inovasi Teknologi Dan Material Terbarukan Menuju Infrastruktur Yang Aman Terhadap Bencana Dan Ramah Lingkungan, 490–497. https://publikasiilmiah.ums.ac.id/xmlui/bitstream/handle/11617/12747/503_CEEDRIMSREV_eBook_ProsidingCEEDRIMS2021_rev300821.pdf?sequence=1&isAllowed=y
Basuki, A. T. (2014). Penggunaan SPSS dalam Statistik. In Danisa Media (Vol. 1).
Djatnika, S. S. (2018). Kontrak Kerja Konstruksi.
Hamid, R. S., & Anwar, S. M. (2019). Structural Equation Modeling (SEM) Berbasis Varian.
Harahap, L. K. (2020). Analisis SEM (Structural Equation Modelling) Dengan SMARTPLS (Partial Least Square). 1, 1.
Lestari, I. G. A. A. I. (2013). Perbandingan Kontrak Kontruksi Indonesia dengan Kontrak Konstruksi Internasional. Ganec Swara, 7(2), 64–69.
Nasrul, & Mulyadi, B. (2019). Tinjauan Addendum Waktu Pelaksanaan Proyek Pembangunan Jembatan Kampung Baru Nan Xx Kota Padang. Rang Teknik, 2(2), 221–226.
Sari, A. N., & Suryan, V. (2021). Pandemi Covid-19: Dampak terhadap Pekerjaan Konstruksi. Jurnal Talenta Sipil, 4(2), 214–220. https://doi.org/10.33087/talentasipil.v4i2.77
Suadnyana, P. (2021). Tugas Akhir. Universitas Pendidikan Nasional.
UU 2 TAHUN 2017 Jasa Konstruksi, (2017).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 I Komang Agus Ariana, Ravika Nur Melinda, Dewa Ayu Putu Adhiya Garini Putri , Putu Ariawan
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.